ENDS reconstruction of the substation `Forest` in the Sverdlovsk region
Specialists of RDK `` `ES completed work on 110/6 kV` Forest `dir in the Sverdlovsk region. At the site is completely made battery installation, the remaining work is going as scheduled.
Work on the reconstruction of the substation `Forest` dir in the Sverdlovsk region began in late April 2012. Customer object is re-equipment production department `Artemovskie electrical networks#39; branch of IDGC of Urals` `-` `Sverdlovenergo.
At the substation mounted concrete fence, works on installation of the sump. In the substation control building mounted panel board AC rectifier, made their adjustment. At the substation 110 kV circuit breakers installed the first section, the company#39;s specialists have started their adjustment. Also on the first section of paved power and control cable.
The company#39;s specialists have replaced the old battery, which was in poor condition, the battery type GROE.
Completion of works is planned for September 2012. Reconstruction of the substation is needed to improve the reliability of power supply located in Rezhevsky urban district.