KYIVENERGO `TETS5 IMPLEMENTED AT THE THREE-STAGE WATER PURIFICATION SYSTEM

`` KYIVENERGO introduced at CHP-5 three-stage water purification system
KYIVENERGO `TETS5 IMPLEMENTED AT THE THREE-STAGE WATER PURIFICATION SYSTEM

The treated water will be used for heating the city, as well as to feed the four power station boilers. With the new technology can purify the water of 1200 tons per hour. Today, therefore, the chemical plant TPP-5 - the only Ukrainian chemical plant that uses membrane technology treatment of such power.

In the reconstruction of chemical plant invested about 25 million USD. These funds, according to experts of the company, will pay off in 2-3 years.

`These investments are very important both for the company and for the city. After all, as a result, they give a significant economic and environmental benefits. We save money for the purchase of chemicals, the volume is significantly reduced, minimizing the impact on the environment TPP `, - the technical director of PJSC Kyivenergo` `Alexander Zaitsev.

Recall one of the stages of implementing a modern system of water treatment using reverse osmosis technology in CHP-5 was introduced last year.