Monday, January 13, 2014

KUBAN POWER PLANT CASCADE HANDLE ROUTINE REPAIRS OF ALL GIDROAGREGAT

Kuban power plant cascade handle routine repairs of all GIDROAGREGAT
KUBAN POWER PLANT CASCADE HANDLE ROUTINE REPAIRS OF ALL GIDROAGREGAT

During the first 9 months of 2012, the station of the branch of RusHydro `` - `` Kuban power plant cascade developed 1,199,500,000 kWh of electricity, accounting for 101.2% of the planned target. In the last year of production for the nine months amounted to 1.1505 billion kWh, or 96.1% of the plan.

`To date, completed work on the third and fifth hydroelectric pumped storage, second and third - GES-3, the first - GES-4 and the second hydraulic unit Svistuhinskaya station. The cycle is complete overhaul of hydroelectric? 3 Svistuhinskaya HPS `- said Acting Director of JSC RusHydro `` - `` Kuban power plant cascade Gennady Sergeyev.

In September of 2012 was finished repairing the machine room Sengileyevskaya HPP and HPP headrace Egorlikskaya. At the waterworks HPP-2, GES-3 and GES-4 refurbished plates, fixing the dam daily regulation. The bed of the end portion of the discharge channel Barsuchkovskiy cleared of sediment, reinforced slopes of its shores.

In addition to the planned activities are carried out routine repairs of all hydroelectric power plant cascade of Kuban. Experts examine the flow-through parts, check the mounting of the impeller to the shaft of the turbine, conduct an audit of the turbine bearing and turbine shaft seal. In carrying out routine maintenance of hydraulic controlled by the guide bearings, thrust bearing and generator cooling system, maslovann upper and lower bracket.

As part of the comprehensive reconstruction of Cascade Kuban power plant to date, conducted a survey of the main and auxiliary equipment, reconnaissance survey and collection of baseline data on hydraulic structures and the surrounding area. Also, project documentation for the replacement switch on the HPP-2, a power transformer on GES-1 and the construction of idle water Egorlikskaya HPP. In November 2012 at the Alstom factory quality control will surge and line portals Sengileyevskaya HPP HPP-4.