By this time, have been restored to standard indicators parameters circulation of the water and the heating mode of Vladimir. According to the operative data of a set of measures of adjustment modes of in-heating systems for disabled facilities was completed by 7.00 today.

Recall that on January 14 this year recorded an increase recharge water network. During the inspection, it was discovered the flooding of the chamber? 117 (street of barracks). Specialists it was decided to carry out repair work on the site. January 15 at 7:30 am service began to shut down the site.


By 11.50 were completed excavation and removal of the damaged section of the pipeline. After that repair crews began replacing the backbone area.

In the course of the work has been replaced 3.5 m pipe diameter of 700 mm. In addressing the defect attended 10 units of special equipment, two maintenance crews, the total number of the professionals involved - 30 people.