NOW HAVE OWN Izhevsk plant of its own power
Electricity generation is performed using two block back-pressure steam turbine. Power turbine - 3000 and 3500 kW / h This power is enough to power the assembly shop Grant, body paint shop and press production (surplus transferred to the city#39;s power grid). The saved Izhevsk plant can reach up to 30 million rubles a year.
`Running its own power - one of the steps comprehensive modernization. The use of electricity self-generation of energy security and increases the efficiency of automobile. The company extended period of time is a reliable supplier of heat and hot water city.
And now we come to the wholesale power market, increasing the volatility of our car factory `, - said General Director of the Izhevsk plant Alexey Alexeev.
`Udmurtia is energodefittsitnym region. The introduction of new capacity - an important event not only for the district and the city, but for the whole country in general. Currently in Europe prohibits putting into operation of the boiler without the possibility of cogeneration. So I sincerely rejoice launch Autazavadski boiler turbine section, which allows the company to use its own electricity and reduce the burden on the urban grid.
Izhevsk plant becomes a model for national companies in terms of generating capacity #39;, - said the Minister of Industry and Energy of the Republic of Udmurtia Oleg Radzivonau.
Construction of the turbine department began in 2008 the forces of `` IzhAuto, but because of the bankruptcy of the last was suspended. Resumed in February 2012 already on the company `` OAS (group AvtoVAZ), and a year later, in February 2013, were carried out commissioning and test run of the equipment.
Investment Company `` OAS in the project amounted to 130 million rubles.