Wednesday, December 4, 2013

GORELECTROSET `LIQUIDATE DEFICIT OF ENERGY SUPPLY IN SOME AREAS NIZHNEVARTOVSKOYE

`` Gorelectroset liquidate deficit of energy supply in some areas Nizhnevartovskoye
GORELECTROSET `LIQUIDATE DEFICIT OF ENERGY SUPPLY IN SOME AREAS NIZHNEVARTOVSKOYE

At the core of the document - the analysis of current and accurate forecast of future needs of urban energy market for the next five years. In this spring, agreeing on the parameters of the program, the City and Energy took into account not only the development plans of the municipality, but also the interests of entrepreneurs, misleading and planning to put into operation new facilities in the city.

The main focus of investments of `` Gorelectroset in 2012 was the construction of transmission facilities to ensure the commissioning of new residential areas in the eastern planning area, the residential development at 9 and 9a-districts (quarter `Central`).

At the moment, made the construction of six transformer substations with a total capacity of 11.1 MVA and laid more than 3 km. cable lines with voltage of 10 kV. Started the construction of a transformer substation 35/10 kV closed nominal capacity of 32 MVA (PS `Jubilee #39;) in the 9th district and the planned commissioning in 2013.

In order to provide electricity to newly constructed private housing in the old part of the city of Nizhnevartovsk finished construction of 10 kV distribution center with built-in transformer substation 2 MVA (RP Dagestan ``).

Also in the interests of small and medium-sized businesses and to improve the energy supply of the Western industrial unit is building of a new 10 kV distribution point in the 13th panel (for st. Internationalist) and a transformer substation 6/0, 4 kV capacity of 2.1 MVA in production base Synthesis `Company`. All this will help to eliminate the resulting deficit of energy supply today in those areas of the city.