Monday, November 25, 2013

JUZHKUZBASSUGOL `LAUNCHES NEW LAVA AT MINE` `ALARDINSKAJA

`` JUzhkuzbassugol Launches New lava AT MINE `` Alardinskaja
JUZHKUZBASSUGOL `LAUNCHES NEW LAVA AT MINE` `ALARDINSKAJA

The average monthly load on the lava will be 150-160 thousand tons of coal. Lava 06/01/21 was the second longwall working for the mine `Alardinskaja`: the current lava 3-32 monthly issue of 90 million tons of coal. The main consumer of coal mines are the `` Alardinskaja smelters Eurasia.

In the construction of lava were involved in the whole collective force of the mine. Preparation of a new stope was carried out in compliance with all standards of industrial health and safety, have made the necessary tunneling, mining and capital, decontamination works. After about 12 km of mine workings, to perform complex assembly work, resolved issues airing.


The new lava installed modern equipment made in Poland, England and Germany.