COAL MINING MI

Coal mining IM.TIHOVA BEGIN IN 2014
COAL MINING MI

In the Company `Mine after. SD Tihova `(located under the Company` Coke-Mining #39;, related to the Group COKE), construction of the surface complex and the launch of the new equipment. Maintained capital development and production of the first lava. Of the 28,500 meters of completed 7674 m, of which c beginning of 2012 until the beginning of November - 4322 running meters.


The maximum depth of mining from the surface is 120 meters.

Total investment in the construction of the mine named SD Tihova, considering the cost of a license was about 5.7 billion rubles (about 183.5 million U.S. dollars).

In 2012, the works on the reconstruction of temporary modular buildings and residential complex completed construction of a discharge fan installation. Included in the complex system of heating the surface of the object, the repair shop of mining equipment and production and the local Fire Station.

For underground development at the mine. SD Tihova used seven tunneling machines. With the mine `` Butovskaya arrived extra roadheader DOSCO (UK).


For transportation in mine workings are three diesel-hydraulic locomotives. Also on mine there are seven belt conveyors. An agreement with a group of FAMUR (Poland) for the manufacture and supply of main conveyor belt Pioma 1,400.


To ensure mining compressed air in the mine installed modular compressor stations with compressors DAN 200SHM.

At the time of launch of the first startup complex at company `Mine after. SD Tihova `will work 1,075 people. Today, of the 689 staff units actually occupied by 476.

Start of production at the mine. SD Tihova scheduled for 2014 with the aim of reducing construction time and reduce the volume of mining operations decided to make a run mine in three stages. The first start-up complex includes an autopsy, the training and testing of the first unit of the reservoir?


23. Production capacity at this stage will be 1500 tons of coal per year. Launch complex provides an autopsy, preparation and launch of the second stope on a layer?


26 and exit at a production capacity of 2.1 million tons of coal a year. On the third stage of the autopsy will take place, the preparation and launch of the third stope in the second block of the formation? 23.


According to plan production capacity will reach 3,000,000 tons of coal per year.